Open-Air Community Theatre
Reutlingen, Germany
- Architects
- 4a Architekten
- Location
- Reutlingen, Germany
- Year
- 2008
New construction of covered seating area with ticket office.
The covered seating area at the heart of the forest has a “light, open and modern” design, entirely in keeping with the clients’ wishes. The movement of the dynamic structure symbolises growth and change – the theatre blends into the natural surroundings of the forest. Approximately 1.000 seats for theatre audiences are arranged beneath the generous self-supporting roof structure. The green colour of the Alucobond cladding lends a natural appearance to the design and integrates the structure into its surroundings. Sloping joints in the metal cladding follow a natural (dis-)order, the colouring and structure of the forest being picked up in the façade.
Client
Naturtheater Reutlingen e.V.
Construction period
09/2007 to 06/2008
Construction costs
approx. 1.1 million euros
Gross floor area
approx. 1065 m²
Gross cubic volume
approx. 6797 m³
Service phases
1 to 9
Project team
Barbara Croonenberg, Rüdiger Ostermayer
Awards
Baden-Württemberg timber construction award 2009
Exemplary constructions in Reutlingen 2001-2008
Related Projects
Magazine
-
Winners of the 5th Simon Architecture Prize
1 week ago
-
2024, The Year in …
1 week ago
-
Raising the (White) Bar
1 week ago
-
Architects Building Laws
1 week ago